A self-managing team, which comprises of a small group of shop floor people either from the same or different work areas, is recognized for its excellence in managing process activities.

MOTO QUALITY

Sentiasa mempertingkatkan pengendalian sistem pengurusan kualiti demi mencapai kepuasan pelanggan.

POLISI QUALITY

Memenuhi keperluan pelanggan dan pemegang saham . Sentiasa mempertingkatkan keberkesanan sistem pengurusan kualiti . Memcapai kepuasan pelanggan . Memperkembangkan kesedaran jenama syarikat.

Friday, July 23, 2010

CIP-9 at Chee Wah showroom

What is Report?
- Who need report?
- Why we need report?
- When we need report?
- What we should report?
- How we should report?

Segregate into 2 groups:
1) Reported by LimTH
- Who need report? - Everyone need report
- Why we need report? - To analyze for improvement
- When we need report? - Everyday
- What we should report? - Plan/Do/Check/Action
- How we should report? - Root cause & Data

2) Reported by LeeEK
- Who need report? - Operator/Supervisor/Manager/Management Level
- Why we need report? - Analyze for improvement/Root cause, Convert data into useful information/For reference and guideline
- When we need report? - Daily/Monthly/Yearly, When there is a task
- What we should report? - Key para meter, True picture/scenario
- How we should report? - Simple, Readable

Presented by FM
- Who need report? - PC/Supervisor/Leader
- Why we need report? - To analyze status, to review effectiveness of previous action result, reformulate action plan
- When we need report? - Mid of the duration allocated
- What we should report? - Set criteria (below 70% from target, quality issue, 4Ms issues)
- How we should report? - Format on written, Verbal on immediate

Report from Supervisor:-
Exercise Book
- To brief KPI rates
- Need to do 5S
- Need potential operators
- Need more consistent J/S from planner (less size change)

Pad
- Short run job is increasing
- Training on new operator

Ruling - Need sufficient roller

Printing - Need to improve on colour setting

Manual
- Need to increase workforce
- Enforce on 5S to create space

Binding
- Training on new operator
- Enforce on 5S to create space

Reported from Quality Assurance
- Briefed on wastage report

Reported from Engineering
- Briefed on machine target speed

Reported from Head of PC
- Emphasis on 3M - Machine, Man Power and Method
- Strictly follow WI on training
- Maintenance/Repair must be prompt and follow schedule

Reported/Conclusion from FM
- All supervisor enforce to use on training manual/Work Instruction "WI"
- Review the operator
- 5S
- Enforce on Lean Concept